Relativity tests Terran R second stage, completes structural qualifications ahead of inaugural launch

NASASpaceFlight.com ·

Relativity Space is advancing Terran R’s flight one hardware and ground infrastructure across NASA’s Stennis Space Center, Long Beach, and Cape Canaveral Space Force Station as the company works toward the rocket’s inaugural launch. Recent work includes a milestone second-stage hot-fire campaign in Mississippi, major structural and engine integration in California, and steady pad outfitting at Florida’s Launch Complex 16.

Relativity completes Terran R second stage testing

Terran R’s flight one second stage recently completed a 10-second hot-fire test on the A2 test stand at NASA’s Stennis Space Center in October, the stand’s first stage-level test since 1970.

On test day, Relativity teams loaded propellant and helium and “moved into terminal count without a hold,” according to the company, before firing the Aeon V engine for the planned 10 seconds. Teams then outfitted the stage into a flight-representative configuration for longer-duration testing, culminating in a successful, first-attempt Mission Duty Cycle (MDC) hot fire lasting over 400 seconds — the full burn duration required during upper-stage vacuum flight.

🔥 Hot metal. Blue fire. Stage 2 completed its mission duty cycle on the first try: a 400+ second burn and coast demo including an igniter hot fire, demonstrating everything it needs to do in flight. pic.twitter.com/J1z07mZnyO

— Relativity Space (@relativityspace) November 13, 2026

Built in the 1960s to test the Saturn V’s S-II second stage, the A2 stand was later reconfigured after the Apollo program to test individual Space Shuttle Main Engines. Elsewhere at Stennis, engine acceptance testing continues on the R stand for flight two’s Aeon R engines.

Terran R first stage development continues

At Relativity’s headquarters and factory in Long Beach, California, Terran R’s first stage is nearing structural completion.

Engineers have completed the breakover of flight one’s thrust structure, rotating the assembly from vertical to horizontal with all 13 Aeon R engines, fluid lines, and avionics installed. Following breakover, technicians began mating the thrust structure to the first stage tankage, while Relativity’s in-house paint team began applying the stage’s livery.

Diagram of Terran R. (Credit: Relativity Space)

Alongside progress on the first stage, Relativity has completed structural testing of its interstage at Long Beach using the structural test stand “Tender Loving Crusher.” The interstage endured millions of pounds of compressive load, grid fin punch loads, loads across raceway fluids, the liquid oxygen (LOX) vent, and composite overwrapped pressure vessels, plus separation latch preloads above flight levels.

See Also

This closed out the structural qualification for all primary flight one structures. Relativity is also bonding the thermal protection system to the interstage and welding the lattice-shaped grid fins.

Launch Complex 16 nears completion

Renovations of Launch Complex 16 (LC-16) at the Cape Canaveral Space Force Station, from the Terran 1 to the Terran R infrastructure, are nearing completion. On the launch mount, steel framing is complete on the launch table.

Alongside this, the down conductor towers (a crucial part of the lightning protection system) are finished. With the vertical towers in place, the next step is stringing overhead catenary wires between the 161 m towers to form a protective canopy over the pad.

Once those cables are tensioned and topped with air terminals, engineers will tie surrounding pad structures into the main grounding grid, run electrical resistance tests to ensure lightning strikes safely dissipate into the 30 m foundations, and secure final range safety sign-off ahead of launch operations.

October was a full month of progress for Terran R. 🚀 The historic A2 test stand – built for Apollo and later used for Space Shuttle engine testing – is back in action, now firing for Terran R.

Plus:
✅ Interstage structural testing complete
✅ Thrust structure breakover + mate… pic.twitter.com/GjxSihvtUN

— Relativity Space (@relativityspace) November 16, 2026

As Terran R is horizontally integrated, Relativity will use a transporter erector (TE) to roll the vehicle to the pad and raise it upright. In its October update, the company noted that second stage fluid systems have been installed in the upper strongback, and the second TE lift cylinder has arrived on site — one of a pair of massive hydraulic actuators that will pivot the strongback and Terran R from horizontal to vertical on the launch table.

At the propellant farms, teams cryo-shocked the LOX tanks, filling them with cryogenic fluid to verify they can withstand the extreme cold temperatures of cryogenic fluids ahead of commissioning.

Relativity looks ahead to future missions

Getting Terran R’s Flight One hardware and LC-16 ground systems ready is key to clearing a growing manifest of commercial and government missions. That backlog expanded with a high-profile lunar assignment on Nov. 7 when NASA awarded Impulse Space a firm-fixed-price task order under its Venture-Class Acquisition of Dedicated and Rideshare (VADR) contract.

Next stop: the Moon. 🚀 We’re partnering with @GoToImpulse on a lunar mission for @NASAMoonBase ! Terran R will launch Helios and lander vehicles to orbit for the first leg of the journey towards humanity’s first permanent lunar outpost.

Learn more about the mission:… pic.twitter.com/jydkpvtEjb

— Relativity Space (@relativityspace) November 7, 2026

The task order calls for Impulse’s Helios kick stage and lunar lander to fly aboard Terran R beginning in 2028. Serving as the prime contractor on the task order to support NASA’s Moon Base program, Impulse will use Terran R to launch the vehicles into orbit, then deploy the payloads into target cislunar orbits and test cargo delivery near the lunar south pole.